Resources For Teachers For Tutors For Students & Parents Pricing
Year 12 Maths Standard 2 (2027) Critical path analysis

Gantt Charts

ACCOUNT REQUIRED

Unlock all 20 questions & worked solutions

You're viewing a free preview. Create an account to access the complete question set, step-by-step solutions, and progress tracking.

All Questions

Access the full question set for every topic.

Worked Solutions

Step-by-step explanations for every answer.

Track Progress

Mark questions right or wrong and monitor your growth.

It's Free

No credit card required - sign up in under a minute.

Question 1
189807

The Gantt chart shows a backyard patio project. Each bar starts at the activity's earliest start time and its length is the activity's duration in days; a grey extension is that activity's float, and critical activities are drawn in red. What is the earliest start time of activity \(D\)?

Gantt chart for the patio project, activities A to FRead the start day of activity D off its bar. 0 1 2 3 4 5 6 7 8 9 10 11 12 time (days) A B C D E F
4
 \(\text{ days}\) 1 mark